Drydock No. 4 Cassion Repair Aker Philadelphia Shipyard March 2008
At the request of Aker Shipyard Philadelphia, Atlantic Subsea constructed a 175 foot long, 60 foot high steel cofferdam wall in 28 days. The cofferdam wall was to temporarily seal the dry-dock and keep it dewatered for the shipbuilding activity. Through design changes, we enabled Aker to successfully continue use of the dry-dock for ship building.
Autoberth Mooring Dolphin Diamond State Port Corp. 2009
In 2009, we were contracted by the DSPC to build a mooring dolphin to accommodate larger ships at the Auto Mooring Berth on the Delaware. The dolphin housed state of the art mooring winches to accommodate larger ships on this berth.
Lafarge Buchanan FGD Conversion PCL Construction Services, Inc. August 2009
In the process of converting Lafarge’s gypsum plant to fly-ash, their marine terminal at Buchanan had to be upgraded to receive bigger ships. In the process of upgrading the marine structures we constructed a crane pier and 3 new mooring dolphins. We also repaired existing structures by underpinned piles. We also transported, installed and assembled a 200 ton crane from Rotterdam on the newly constructed Unloading platform.
Steel Sheet Bulkhead Hess Corporation May 2010
This was a design build project for Hess Corporation. Due to environmental impacts and restricted timelines we completed the project under budget and ahead of anticipated completion time.